qtech_logo_t

Defence Acquisition Procedure – 2020

The first Defence Procurement Procedures (DPP) were promulgated in the year 2002 and has since been revised periodically to provide impetus to the growing domestic industry and achieve enhanced self-reliance in defence manufacturing. Recently the defence ministry released the Defence Acquisition Procedure (DAP)-2020, a renamed version of the Defence Procurement Policy (DPP) to be applicable with effect from October 1, 2020. It is said to be aligned with the vision of the Government of Atmanirbhar Bharat and empowering Indian domestic industry through Make in India initiative with the ultimate aim of turning India into a global manufacturing hub. DAP 2020 has included some provisions like increase in FDI and others  to enhance manufacturing hubs both for import substitution and exports, it is to be seen how far these aims are achieved.

Specific reforms incorporated in the recent version are as under:-

List of Weapons/Platforms for Ban on Import

Relevant incorporation has been done in the DAP to ensure that NO equipment as mentioned in the list is procured ex import post timelines notified.

Indigenisation of Imported Spares

  • Request For Information

RFI stage will explore willingness of the prospective foreign vendors to progressively undertake manufacture and setup an indigenous eco system at the spares/sub component level.

  • New Category of Buy (Global – Manufacture in India)

The new category incorporates ‘manufacture of either the entire/part of the equipment or spares/assemblies/sub-assemblies/Maintenance, Repair and Overhaul (MRO) facility for the equipment, through its subsidiary in India.

  • Co-production through IGA

This enables establishment of co-production facilities through IGA achieving ‘Import Substitution’ and reduce Life Cycle Cost.

  • Contractual Enablement. Buyer’s Right to optimise Life Cycle Support costs and system enhancements through indigenous eco system incorporated.

FDI in Defence Manufacturing

 With the announcement of new FDI Policy, suitable provisions have been incorporated like new category ‘Buy (Global – Manufacture in India)’ done to encourage foreign OEMs to setup ‘manufacturing/maintenance entities’ through its subsidiary in India while enabling requisite protections to domestic industry.

Time Bound Defence Procurement Process and Faster Decision Making

As part of the Defence Reforms announced in the Atmanirbhar Abhiyan, setting up of a PMU has been mandated to support contract management. The PMU will facilitate obtaining advisory and consultancy support in specified areas to streamline Acquisition process. Other issues included in these reforms are:-

Realistic Setting of GSQRs of Weapons/ Platforms

The process of formulation of SQRs has been further refined with greater emphasis on identifying verifiable parameters based on analysis of ‘Comparative’ equipment available in the World and Domestic markets.

Simplification of Trial Procedures

DAP 2020 emphasises the need to conduct trials with an objective to nurture competition based on the principles of transparency, fairness and equal opportunities to all and not as a process of elimination.

Ease of Doing Business One of the key focus areas of the review was to implement ‘Ease of Doing Business’ with emphasis on simplification, delegation and making the process industry friendly with certain specific provisions incorporated:-

Procedural Changes

  • Single stage accord of AoN in all cases upto Rs 500 crores has been instituted thereby reducing time.
  • FTP cases, post accord of AoN, will be progressed as per delegated powers thereby reducing the procurement cycle considerably.
  • In Planning Process, LTIPP has been re-designated as Integrated Capability Development Plan (ICDP) covering planning period of ten years instead of 15 years.

Request for Proposal (RFP) and Standard Contract Document (SCD)

 Certain measures to provide clarity and alignment of requirements as also enabling provisions have been incorporated in the RFP and SCD in terms of Flow Chart driven guidelines, provision of in-storage preservation and termination of contracts in cases where projects are not progressing as per pre–defined milestones.

Salient features of DAP 2020

Reservation in Categories for Indian Vendors

 The categories of Buy(Indian-IDDM), Make I, Make II, Production Agency in Design & Development, OFB/DPSU and SP model will be exclusively reserved for Indian Vendors meeting the criteria of Ownership and Control by resident Indian Citizens with FDI not more than 49%. This reservation will provide exclusivity in participation to domestic Indian industry.

Enhancement of Indigenous Content

  • Overall Enhancement in Indigenous Content (IC).
  • IC Verification. A simple and practical verification process has been instituted and IC will now be calculated on ‘Base Contract Price’ i.e. Total Contract Price less taxes & duties.
  • Indigenous Military Material. Promoting use of indigenous military material with provisions for examination of platforms and other equipment/ systems and reward for vendors for using indigenous raw material.
  • Indigenous Software. Provision for exploring options for operating base applications like Fire Control System, Radars, Encryption, Communications etc on indigenous software in Buy (Indian- IDDM) & Buy (Indian) cases has been included.

Rationalisation of Trial and Testing Procedures

  • Testing equipment based on its employability and for other conditions appropriate certifications confirming functional effectiveness may be obtained.
  • Scope of Trials will be restricted to physical evaluation of core operational parameters, other parameters may be evaluated based on vendor certification, certification by accredited laboratories, computer simulations of parameters.
  • Avoid duplication of trials and waiver will be granted based on Certificates of Conformance. Ensure simultaneity of various Trials and wherever feasible, entire trials be conducted by a Combine Trial Team in order to save time.
  • Requisite opportunity will be afforded to participating vendors to rectify shortcomings/faults during the Trials with permission to carry out repairs.
  • Request For Proposal will apprise vendors to submit draft Acceptance Test Procedure (ATP), to be finalised by QA agency during Technical Trials itself. Sample size for destructive tests including the aspect of cost to be borne by seller will be stated upfront in the RFP for vendor.
  • No repetition of inspections will be done especially during acceptance of equipment. Third Party Inspections will also be carried out.

Make & Innovation

  • Make I (Government Funded upto 70%). Laying down a cap of Rs 250 crore/DA and selection of DAs based on bidding criteria.
  • Make II (Industry Funded) for production of indigenously designed & developed weapons/equipment/systems/platforms along with sub components/assemblies.
  • Make III (Indigenously Manufactured) category for manufacture of equipment/platforms or spares/assemblies/sub-assemblies for enabling import substitution.
  • Procurement of prototypes developed through ‘Innovation’ under various initiatives like iDEX, Technology Development Fund and Internal Services Organisations has been facilitated.

Design & Development

A separate dedicated chapter has been incorporated in the DAP 2020 for acquisition of systems Designed and Developed by DRDO/DPSUs/OFB. Single Stage Trials to reduce timelines and laying greater emphasis on evaluation through certification and simulation is envisaged.

Industry Friendly Commercial Terms

  • Price Variation Clause has been incorporated for large and protracted contracts in order to avert inflated initial quotes by vendors and arriving at a realistic price of the project.
  • Payments to Vendors.  Suitable provisions like parallel processing of documents by SHQ/PCDA through digital verification, within laid down timelines, has been included to ensure timely payment to vendors. Payments to Indian industry have been aligned with foreign industry.

Offsets

The Offset guidelines have been revised, wherein preference will be given to manufacture of complete defence products over components and various multipliers have been added to give incentivisation in discharge of Offsets.

New Chapters

  • ‘Information Communication Technology’. Peculiar issues related to procurement of ICT intensive equipment especially of Interoperability & Built-in Upgradability, enhanced security requirements and change management have been included.
  • Leasing. A new category introduced to enable operating of assets without owning thereby, substitute huge initial capital outlays.
  • Post Contact Management. To formalise procedures post signing of contract with respect to inspections, levying of Liquidity Damages, Contract Amendments etc.
  • Other Capital Procurement Procedure. A new procedure has been included as a new chapter in DAP and structured as an enabling provision for Services to procure essential items through Capital Budget under a simplified procedure in a time bound manner.

In fact, DAP 2020 which has been formulated post interactions over a year, claimed to be  an enabler & industry friendly procedure aligned with Government of India’s vision of Atmanirbhar Bharat & impetus to Make in India. The  real concern is will the 681-page  procedure  accelerate material procurements  through the arduous processes of  procurements and will instills  confidence and  meet aspirations of stakeholders across the spectrum. Seemingly the wording changes and adding Atmanirbhar Bharat a good political slogan mean nothing, with same official dispensation with zero ground effects.